Frimley Park Hospital is starting a major refurbishment of all its main corridors from Monday 19 June.
Walls will be finished and redecorated, handrails and bump boards replaced and floors will be resurfaced. The work will involve parts of the floor being dug up and replaced, which may result in some noise.
The work will be carried out in stages with single sections of the corridor closed off at each time. The complete programme of work is scheduled to last four months.
We apologise in advance for any inconvenience his may cause. Please check the signage for diversion routes, or ask at main reception for advice. Please feel free to stop and ask our staff, who will be happy to help visitors who need it.
Main corridors at Frimley are arranged in a quadrant over two storeys. They are colour coded as Yellow Street, Green Street, Red Street and Blue Street (clockwise from the Main Entrance route). Grey Street comes off the corner of Yellow and Green Street, linking the pharmacy on the ground floor and F14/Parkside outpatients on the upper floor.
The section starting on Monday 19 June will be on Grey Street upper floor and will last several days.